Adding water to ready-mixed concrete
Generally, it is not a good idea to add extra water to ready-mixed concrete once it has arrived on site.

Generally, it is not a good idea to add extra water to ready-mixed concrete once it has arrived on site.
For freeze-thaw resisting concrete, the minimum specified entrained air content depends on the maximum aggregate size and is shown below. The allowable test result range is also given.
There is often debate about the time limit between placing fresh concrete against fresh concrete already placed and compacted i.e. minimising the risk of a cold joint being formed.
In cold weather, it may be an advantage to raise the temperature of the fresh concrete at the batching plant so that the concrete retains a sufficient temperature to promote setting and strength development to off-set the risk damage caused by early age freezing. Heating the mixing water is the simple way to warm the fresh concrete.
The sampling and testing of fresh concrete for consistence (workability) and casting cubes for strength testing must be carried out correctly so that the results are representative of the concrete supplied.
Steel or macro synthetic fibres may be added to the concrete either at the ready-mixed plant or to the mixer truck on site. The addition of fibres to the concrete should be in accordance with an agreed method statement, to ensure that the fibres are adequately distributed throughout the concrete, there are no fibre balls that may cause pump blockages and the quality of the final concrete is not unduly affected.

Batching is similar to that of normal concrete, generally from ready-mixed concrete outlets. Workability is commonly between 50 mm and 100 mm slump and the concrete can be easily placed by skip or chute. However, due to the low bulk density of the aggregate, separation from the mortar tends to occur especially at higher workabilities.
BS 8500-2:2023 Concrete –
BS 8500:2023 has dropped the 2-hour ´