Detailing symbols (previous & current)
The symbols used on reinforcement drawings to indicate the type of reinforcement have been specified in various Standards over the years, as indicated below:
The symbols used on reinforcement drawings to indicate the type of reinforcement have been specified in various Standards over the years, as indicated below:
The reinforcement stresses (in tension) to be used in design, as specified in the Code current at the time, have changed over the years as indicated below. Note that design stresses in compression were lower than in tension until 1972. For information on the 
The main benefit of prestressing is that the build up of tension under service loads and possible cracking may be avoided or reduced to a low level. The effective stiffness of the cross-section is increased, leading to a reduction in deflections. This is particularly important for long-span structures and results in lower overall depths. Deflected tendons can enhance the shear capacity of sections, with the vertical component of the prestressing force carrying a proportion of the load. Prestressing should enhance the fatigue resistance of structures subjected to repeated loads, such as bridges. Finally, prestressing is beneficial in many forms of segmental construction
In pre-tensioning the prestressing tendons are tensioned and anchored between fixed supports before the concrete is cast. The concrete is either cast in moulds or formed by an extrusion or slip-form process to form the required cross-section. When the concrete has gained sufficient strength, the tendons are released from the supports. The prestressing force is transferred from the tendons to the concrete by the bond between the tendon and concrete. The transfer occurs over a short transmission length at each end of the concrete member. Elastic shortening of the member will lead to some loss of the prestressing force.
In post-tensioning, the prestressing tendons, which may be located inside or outside the concrete, are tensioned after the concrete has hardened. Internal tendons are contained within ducts or sheaths cast into the concrete and can be arranged to follow the most appropriate profile to suit the applied external loading. External tendons are arranged in a series of straight lines with changes of direction at specific locations. In all cases the tendons are tensioned using jacks that bear against the exposed face of cast-in anchorages at the ends of the tendon. When the required force has been attained, the tendons are secured at the anchorages, using a system of wedges. The elastic shortening of the concrete that occurs during the tensioning process has no effect on the force in the tendons, but some loss may occur due to draw-in of the anchoring wedges.

Design standards specify the required load capacities of structures and aspects of their in-service performance (such as recommendations for permissible deflections). They also give general methods for design so that structures have an appropriate margin of safety and perform adequately in-service.
The basic principle of prestressed concrete design is that some or all of the concrete cross-section is put into compression during the construction process. The arrangement of pre-compression is such that those areas of the structure that would be expected to go into tension under the loads applied in service (such as the sagging regions of beams) still remain in compression (or in very limited tension).
Calculations for determining the amount of reinforcement required in a concrete member (e.g. a beam or slab) should be in accordance with the appropriate Standard, see ´
The design of the reinforcement for a concrete member will generally lead to the requirement for a variety of shapes as well as straight bars. These will be shown on the reinforcement drawings.