Llyn Celyn is the largest reservoir by volume in Wales, with a capacity of 81 million cubic metres. The £45m reservoir safety scheme is to protect the dam and communities along the River Dee, in the event of an extreme flood.

Concrete Society Awards 2026 logo

Llyn Celyn PMF Flood Conveyance Scheme, North Wales

Llyn Celyn PMF Flood Conveyance Scheme

Project Information

Llyn Celyn is the largest reservoir by volume in Wales, with a capacity of 81 million cubic metres. The £45m reservoir safety scheme is to protect the dam and communities along the River Dee, in the event of an extreme flood.

The project features a new auxiliary spillway, including a culvert beneath the access road and precast concrete tipping gates

  • Nominator Concrete Structure and Floor
  • Client Welsh Water
  • Reinforced Concrete Subcontractor Concrete Structure and Floor
  • Concrete Supplier Cambrian
  • Contractor/Designer/Consultant Mott MacDonald Bentley (MMB)
  • Admixture Supplier Sika
  • Formliners Reckli

Judge’s Comments

Based on the remote site and the weather conditions experienced to deliver the project on time and on budget is a testament to excellent teamwork and communication within the project team,
and an example of how civil engineering projects can be delivered. Careful planning, considerable expertise in concrete and engineering, all ensured that the solution not only met the
brief but went above and beyond.

As Llyn Celyn lies within Snowdonia National Park, the spillway has been carefully designed to blend in with its natural surroundings. All exposed concrete walls have either a patterned concrete finish or stone cladding. The care and attention taken over the formwork liners is commendable considering few people will look closely at the finish, and if they do, many will assume that it is stone block not formed concrete.

Most people will see just a glimpse of this project as they drive along the A4212. This is a real shame, as the attention to detail and quality of finish deserve to be appreciated by more than those who will have access to the site